The start date for our project has finally been decided. We are planning to get underway right after the Canadian Thanksgiving weekend. This is a tentative date as weather can be a deciding factor as to the actual start date. Here is a list of what will be unfolding in the near future:
- signs will be posted indicating a construction site including the appropriate safety signs
- the building permit will be displayed in a visible location
- about 30 small evergreen trees that are on the building site will be moved and transplanted
- a local company will be installing the road approach
- a survey will be completed to mark the precise location of the building
- the foundation contractor will be excavating for the basement
- the geothermal contractor will be drilling holes and installing his piping before freeze up
- the developer will be installing a well, a 2000 gallon holding tank and a grey water disposal system
- the building material will be ordered so it is available when needed, at this time the specific requirements are
- the steel beams
- floor truss system
- roof truss system
- exterior windows and doors
- the local power company (Manitoba Hydro) will be preparing for the electrical service to be installed
- contacting the various trades about the time frame and gauging a tentative date so they may plan accordingly so they will be prepared when they are required